Ealing's current list runs to 108 sets of street works and 21 full road closures. Which roads are shut, how long each runs, and what to check before you drive.
Ealing Council publishes a list of planned street works every week, and the list for the week commencing 6 August 2026 runs to 108 separate sets of works. Of those, 75 were already in progress and 33 were proposed, 21 involve closing a road completely, five close a lane and forty put the traffic under signal control. Twenty-two are the council’s own highway works. Fourteen are HS2.
Most of those entries will be gone within a fortnight. This page concentrates on the ones that will not: the schemes with end dates in October, December, next April and, in two cases, 2028 and 2030. Those are the ones worth planning around.
The works that outlast the week
| Road | Area | Work and who is doing it | Traffic | Ends |
|---|---|---|---|---|
| Old Oak Common Lane | East Acton and Park Royal | HS2 enabling works | Signals and lane restrictions | 31 Dec 2028 |
| Badminton Close | Northolt | HS2 enabling works | Road closed | 2 Apr 2027 |
| Boston Road | Hanwell | Ealing Council highway improvement | Two-way signals | 31 Dec 2026 |
| Uxbridge Road | Southall, Norwood Green | Ealing Council highway improvement | Lane closure | 31 Dec 2026 |
| Gunnersbury Lane | South Acton | Temporary pedestrian crossing | Two-way signals | 24 Nov 2026 |
| Oldfield Lane South | Greenford | SSE mains replacement | Road closed | 9 Oct 2026 |
| Argyle Road | West Ealing, Pitshanger | Thames Water new supply | Multi-way signals | 8 Oct 2026 |
| Southdown Avenue | Hanwell, Northfield | Cadent Gas mains replacement | Multi-way signals | 1 Oct 2026 |
| Lady Margaret Road | Southall | Ealing Council highway improvement | Lane closure | 30 Sep 2026 |
| Leeland Road | West Ealing, Walpole | Ealing Council | Road closed | 26 Sep 2026 |
| Park View Road | Ealing, Hanger Hill | Cadent Gas mains replacement | Two-way signals | 21 Sep 2026 |
| The Broadway | Southall | Affinity Water mains replacement | Multi-way signals | 18 Sep 2026 |
Two of these need a word of explanation.
Old Oak Common Lane is not really a roadworks entry, it is a construction site with a road running through it. Six separate HS2 permits sit on that one street in the current list, the oldest opened in July 2022, and the latest end date on any of them is 31 December 2028. Anyone driving between East Acton and Park Royal should assume signal control on that road for the rest of the decade rather than checking week by week.
Badminton Close in Northolt is the only long-term full closure in the borough. It has been shut for HS2 enabling works since 3 March 2026 and the council lists it as closed until 2 April 2027.
There is one longer entry still. Friary Road in Acton carries a temporary pedestrian crossing under a temporary structure licence, with two-way signals, and the council’s list gives its end date as 31 December 2030. Dates that far out are usually a licence expiry rather than a real programme, but it is on the record as it stands.
What is closed right now
Of the 21 full closures on the current list, most are short utility jobs of a few days. The ones with real duration are Badminton Close in Northolt, Oldfield Lane South in Greenford, closed for SSE mains replacement until 9 October, and Leeland Road in West Ealing, closed by the council until 26 September. Trinity Road in Southall has been closed by the council since 16 April and is listed to 29 August.
On the red routes, Transport for London’s own feed shows a contraflow on the A406 Hanger Lane at the junction of Madeley Road for utility works, running from 12 to 18 August 2026, with traffic reported as flowing well.
The four routes that carry the borough
Roadworks come and go. These do not, and knowing how they behave is more useful than any weekly list.
- A40 Western Avenue runs the full width of the borough, past Northolt, Greenford and Perivale, and it is the fast route in and out. It is a Transport for London red route, so TfL rather than Ealing Council controls what happens on it.
- A406 North Circular and the Hanger Lane gyratory is where the A40 meets the North Circular, in W5. It is also a red route. Anything that happens here backs up onto the A40 within minutes, which is why a minor utility contraflow at Madeley Road is worth knowing about.
- Uxbridge Road is the long east-west local street through Acton, Ealing, West Ealing, Hanwell and Southall. It carries most of the borough’s bus services, and it is the road most often dug up: it appears in the current works list at Southall with a lane closure listed to 31 December 2026.
- Boston Road and the Hanwell corridor is the north-south link down to Brentford and the M4. The council’s own improvement works there run to 31 December 2026.
Before you drive
Every road in Ealing sits inside the Ultra Low Emission Zone. The zone covers all London boroughs, the charge is £12.50 a day for a non-compliant car, van or motorcycle, and it applies 24 hours a day, every day except Christmas Day. Check your vehicle before you assume it is exempt, because the charge is per day, not per journey.
For the works themselves, the council’s own weekly list is the primary source and it is a free PDF: Planned road and street works by Ealing Council and utility companies. It is updated weekly, it names the street, the ward, the contractor, the permit number and a contact number for each job, and it states plainly that minor repairs and emergency works carried out at short notice will not be listed. That last line matters: the list is a plan, not a live picture.
For live conditions, TfL’s status and traffic pages cover the A40, the A406 and the rest of the red route network, which is where the delays that actually matter tend to happen.
What it means for you
If you drive across the borough, the practical reading of the current list is that the Southall and West Ealing ends have the most disruption booked into the autumn: The Broadway, Lady Margaret Road and Uxbridge Road in Southall, Argyle Road and Leeland Road in West Ealing.
If you live in Northolt or East Acton, the HS2 works are the constant. Neither Badminton Close nor Old Oak Common Lane will be clear this year.
If you are commuting, the trains are unaffected by any of this. Ealing Broadway still reaches Paddington in ten minutes and the Elizabeth line runs to Heathrow in twenty-two, which on most mornings beats the A40.
Frequently asked questions
How many roadworks are there in Ealing right now?
The council’s list for the week commencing 6 August 2026 has 108 sets of works, of which 75 were already in progress. Twenty-one involve a full road closure.
Which roads are closed in Ealing?
The long-term closures are Badminton Close in Northolt (HS2, to 2 April 2027), Oldfield Lane South in Greenford (SSE, to 9 October 2026), Leeland Road in West Ealing (to 26 September 2026) and Trinity Road in Southall (to 29 August 2026). The rest of the 21 closures on the list are short utility jobs.
Where can I check Ealing roadworks?
Ealing Council publishes a weekly PDF of planned road and street works listing every permitted job by street and ward. It says minor and emergency works are not included.
How long will the HS2 works in Ealing last?
The Old Oak Common Lane permits in East Acton and Park Royal run to 31 December 2028. The Badminton Close closure in Northolt is listed to 2 April 2027.
Is Ealing in the ULEZ?
Yes. The Ultra Low Emission Zone covers all London boroughs, so every road in Ealing is inside it. A non-compliant vehicle pays £12.50 a day, every day except Christmas Day.
Who do I report a pothole or a badly managed site to?
Ealing Council for borough roads, on 020 8825 6000, which is the contact number against its own entries in the weekly list. The A40 and the A406 are Transport for London’s, not the council’s.
Sources
- Ealing Council, Planned road and street works by Ealing Council and utility companies, the weekly list for the week commencing 6 August 2026, for every scheme, date, contractor and traffic management arrangement on this page.
- Transport for London road disruptions API for the live A406 Hanger Lane contraflow and the red route status.
- TfL Ultra Low Emission Zone for the zone area, the £12.50 daily charge and the operating hours.
- TfL traffic and travel status for live conditions.
End dates on street works are estimates and the council reserves the right to change them. Check the current weekly list before relying on any date here.